CUSD Issues Deductive Change Order for Erickson-Hall Hope ES Project
- Disclosed value
- Total contract not to exceed $20,852,914 after $13,465 deduct change (original $20,866,379)
- From report
- Document date
- Feb 15, 2023
- Term
- 01/23/19 - complete
The 30-second brief
Carlsbad Unified School District approved a second amendment with Erickson-Hall Construction for Hope ES modernization, issuing a deductive change order of $13,465 for unused contingency. The final not-to-exceed contract amount is $20,852,914 for the project term 01/23/19 through completion.
Erickson -hall Construction holds this construction contract with Carlsbad Municipal Schools. Its other public contracts on record include work for Riverside County Office Of Education-School Of Career Education and Carlsbad Unified.
Term as filed: 01/23/19 - complete.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Total contract not to exceed $20,852,914 after $13,465 deduct change (original $20,866,379)
- Document date
- February 15, 2023
- Term
- 01/23/19 - complete
- Source document
- carlsbad-municipal-schools-report-2023-02-15_dd0.pdf (Report)
Erickson -hall Construction's other public contracts
More Carlsbad Municipal Schools contracts
Questions about this contract
Who was awarded the construction contract by Carlsbad Municipal Schools?
Erickson -hall Construction was awarded this construction contract by Carlsbad Municipal Schools, as recorded on February 15, 2023. The contract value is Total contract not to exceed $20,852,914 after $13,465 deduct change (original $20,866,379).
How much is the Erickson -hall Construction contract with Carlsbad Municipal Schools worth?
The Erickson -hall Construction contract with Carlsbad Municipal Schools is valued at Total contract not to exceed $20,852,914 after $13,465 deduct change (original $20,866,379), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in carlsbad-municipal-schools-report-2023-02-15_dd0.pdf (Report), dated February 15, 2023 from Carlsbad Municipal Schools. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Erickson -hall Construction hold?
Erickson -hall Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Carlsbad Municipal Schools currently buying?
Explore Carlsbad Municipal Schools's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.