Twin Lakes Flood Mitigation Contract Amended for Scope and Time
- Disclosed value
- $49,517.00 (change order); revised total contract $20,722,743.09
- From report
- Document date
- Mar 11, 2026
The 30-second brief
Monroe County approved Change Order No. 7 with Ferreira Construction Co. Inc. on the Twin Lakes Flood Mitigation Project, adding $49,517.00 and 20 weather days for king tide impacts and drainage design adjustments. The revised contract now totals $20,722,743.09 with substantial completion extended to June 16, 2026.
Ferreira Construction Co Inc holds this construction contract with Monroe County. Its other public contracts on record include work for City of Mission Viejo and Bergen County.
Term as filed: Original substantial completion 5/5/2026 extended to 6/16/2026 (702 calendar days from 7/15/2024).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $49,517.00 (change order); revised total contract $20,722,743.09
- Document date
- March 11, 2026
- Term
- Original substantial completion 5/5/2026 extended to 6/16/2026 (702 calendar days from 7/15/2024)
- Agency
- Monroe County
- Source document
- Monroe County Report of Monthly Change Orders February 2026 (Report)
Ferreira Construction Co Inc's other public contracts
More Monroe County contracts
Questions about this contract
Who was awarded the construction contract by Monroe County?
Ferreira Construction Co Inc was awarded this construction contract by Monroe County, as recorded on March 11, 2026. The contract value is $49,517.00 (change order); revised total contract $20,722,743.09.
How much is the Ferreira Construction Co Inc contract with Monroe County worth?
The Ferreira Construction Co Inc contract with Monroe County is valued at $49,517.00 (change order); revised total contract $20,722,743.09, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Monroe County Report of Monthly Change Orders February 2026 (Report), dated March 11, 2026 from Monroe County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ferreira Construction Co Inc hold?
Ferreira Construction Co Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Monroe County currently buying?
Explore Monroe County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.