CONTRACTPENDING

Superior Construction to relocate Donelson Pike early

Metropolitan Nashville Airport Authority logoMetropolitan Nashville Airport Authority
Document date
Apr 17, 2024
Term
Until May 31, 2026

The 30-second brief

What it covers

Agreement with TDOT for MNAA to fund an incentive for Superior Construction Company Southeast LLC (Superior) to complete the relocation of Donelson Pike up to 365 days before the current contract completion date of May 31, 2026, and to allow Superior to borrow 200,000 CY NTE of fill material.

Who holds it

Superior Construction Southeast holds this incentive contract with Metropolitan Nashville Airport Authority.

What happens next

Term as filed: Until May 31, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Incentive
Document date
April 17, 2024
Term
Until May 31, 2026
Source document
metropolitan-nashville-airport-authority-joint-board-meeting-agenda-april-17-2024_87f.pdf (Agenda)

Superior Construction Southeast's other public contracts

More Metropolitan Nashville Airport Authority contracts

Questions about this contract

Who was awarded the incentive contract by Metropolitan Nashville Airport Authority?

Superior Construction Southeast was awarded this incentive contract by Metropolitan Nashville Airport Authority, as recorded on April 17, 2024.

What type of contract is this?

This is a Incentive contract, documented as a agenda record.

Where was this contract approved?

This contract appears in metropolitan-nashville-airport-authority-joint-board-meeting-agenda-april-17-2024_87f.pdf (Agenda), dated April 17, 2024 from Metropolitan Nashville Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Superior Construction Southeast hold?

Superior Construction Southeast may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question