CONTRACTPENDING

SB Energy Proposes $5B Data Center Abatement Agreement

Borden County
Disclosed value
$5 billion (Phase 1 project cost); Annual Pilot Payments: at least $1.4M per phase (years 1-10), at least $2.4M total for all phases starting year 5; $720,000/year Emergency Medical payments during abatement; $35,000/month Emergency Services during construction
From report
Document date
Nov 12, 2025
Renews
Free account

The 30-second brief

What it covers

Borden County is negotiating a Chapter 312 abatement agreement with SB Energy for an AI data center, featuring phased 10-year tax abatements, annual Pilot Payments of at least $1.4 million per phase, and $720,000 in emergency medical payments per year. The project is valued at $5 billion for Phase 1 and includes five anticipated phases.

Who holds it

Sb Energy holds this contract with Borden County. Its other public contracts on record include work for Snyder Independent School District and Milam County.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every Borden County contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Amount
$5 billion (Phase 1 project cost); Annual Pilot Payments: at least $1.4M per phase (years 1-10), at least $2.4M total for all phases starting year 5; $720,000/year Emergency Medical payments during abatement; $35,000/month Emergency Services during construction
Document date
November 12, 2025
Term
10-year abatement per phase (years 1-10); Emergency Medical: during abatement; Emergency Services: during construction
Renews
Free account
Vendor
Sb Energy
Source document
Borden County Data Center Abatement Report November 2025 (Report)

Sb Energy's other public contracts

More Borden County contracts

Questions about this contract

Who was awarded the government contract by Borden County?

Sb Energy was awarded this government contract by Borden County, as recorded on November 12, 2025. The contract value is $5 billion (Phase 1 project cost); Annual Pilot Payments: at least $1.4M per phase (years 1-10), at least $2.4M total for all phases starting year 5; $720,000/year Emergency Medical payments during abatement; $35,000/month Emergency Services during construction.

How much is the Sb Energy contract with Borden County worth?

The Sb Energy contract with Borden County is valued at $5 billion (Phase 1 project cost); Annual Pilot Payments: at least $1.4M per phase (years 1-10), at least $2.4M total for all phases starting year 5; $720,000/year Emergency Medical payments during abatement; $35,000/month Emergency Services during construction.

What type of contract is this?

This is a government contract, documented as a report record.

Where was this contract approved?

This contract appears in Borden County Data Center Abatement Report November 2025 (Report), dated November 12, 2025 from Borden County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Sb Energy hold?

Sb Energy may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Borden County currently buying?

Explore Borden County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →