Main Street lighting change order
City of BozemanMontana- Detected
- Oct 20, 2026
- 14 days ago
- Sector
- Capital Projects
- Est. value
- Free account
Get pre-RFPs like this one as they surface.
Get briefs like this freeFree account · 30-second setup · No credit card
From the meeting
The commission considered Change Order 1 for the Pedestrian Crossing and Lighting Projects, Main Street Lighting Design Package 3. The change order adds sidewalk removal and replacement, traffic control, irrigation pipe sleeves, and tree trimming, and increases the Schedule IV contract amount by $24,899 to $281,351. The work was attributed to Montana Lines, Inc.
and extends substantial completion from 90 to 93 days. This is active construction administration and a strong signal for change-order, closeout, and warranty-support opportunities.
- Meeting date
- October 20, 2026
- Agency
- City of Bozeman
More from City of Bozeman
Similar pre-RFPs forming now
Matching work at other agencies, before it reaches a bid portal.
Questions about this project
What is a pre-RFP?
A pre-RFP is an early indicator that a government agency is planning a purchase — a project discussed in a board meeting, a budget line item, a new hire, or a grant award — captured before a formal RFP or bid is published. Acting on pre-RFPs gives SLED and B2G vendors months of lead time to build relationships and shape requirements.
When will City of Bozeman issue an RFP for this project?
Pre-RFPs typically surface 6–18 months before a formal solicitation is published. Civic IQ tracks City of Bozeman's meeting records, agendas, and budgets continuously and updates this pre-RFP as the project moves through the buying cycle toward an RFP.
How can vendors engage with City of Bozeman before the RFP is published?
Vendors who reach out during the planning window can help shape requirements and build relationships with the decision-makers running the project. A free Civic IQ account sends you the pre-RFPs that fit what you sell, with the AI brief and the decision makers for the top matches in each digest.
Where can I find more capital projects government opportunities in Montana?
Civic IQ monitors board meetings, agendas, budgets, and capital plans from 100,000+ state and local agencies and surfaces capital projects pre-RFPs in Montana as soon as they appear — months before they reach bid portals.