Midwest Power Continues Clark Road Booster Station Project
- Disclosed value
- Approximately $1,700,000
- From agendapacket
- Document date
- Oct 27, 2026
The 30-second brief
Midwest Power/Lee Industrial Contracting continues work on YCUA’s Clark Road Water Booster Station Improvements project, awarded in September 2025 at approximately $1.7 million. YCUA reported that schedule delays involved DTE coordination and equipment availability.
Midwest Power/lee Industrial Contracting holds this construction contract with Ypsilanti Community Utilities Authority.
Term as filed: Awarded in September 2025; substantially complete date had not occurred as of September 23, 2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Approximately $1,700,000
- Document date
- October 27, 2026
- Term
- Awarded in September 2025; substantially complete date had not occurred as of September 23, 2026
- Vendor
- Midwest Power/lee Industrial Contracting
- Source document
- Ypsilanti Community Utilities Authority AgendaPacket Board of Commissioners Meeting 2026-10-28 (AgendaPacket)
More Ypsilanti Community Utilities Authority contracts
Questions about this contract
Who was awarded the construction contract by Ypsilanti Community Utilities Authority?
Midwest Power/lee Industrial Contracting was awarded this construction contract by Ypsilanti Community Utilities Authority, as recorded on October 27, 2026. The contract value is Approximately $1,700,000.
How much is the Midwest Power/lee Industrial Contracting contract with Ypsilanti Community Utilities Authority worth?
The Midwest Power/lee Industrial Contracting contract with Ypsilanti Community Utilities Authority is valued at Approximately $1,700,000, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Ypsilanti Community Utilities Authority AgendaPacket Board of Commissioners Meeting 2026-10-28 (AgendaPacket), dated October 27, 2026 from Ypsilanti Community Utilities Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is Ypsilanti Community Utilities Authority currently buying?
Explore Ypsilanti Community Utilities Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.