Wastewater Plant Deadline Extended for Gridor
- Document date
- Apr 12, 2021
The 30-second brief
The Sacred Heart City Council approved a change order granting Gridor a two-week extension to achieve substantial completion on the wastewater treatment plant project, extending the deadline to April 26, 2021. The extension acknowledges ongoing work on sludge tank pumping issues.
GRIDOR holds this construction contract with Town of Sacred Heart. Its other public contracts on record include work for City of Story.
Term as filed: Substantial completion extended to April 26, 2021.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- April 12, 2021
- Term
- Substantial completion extended to April 26, 2021
- Vendor
- GRIDOR
- Agency
- Town of Sacred Heart
- Source document
- city_council_regular_meeting_minutes_april_12_2021.pdf (Minutes)
GRIDOR's other public contracts
More Town of Sacred Heart contracts
Questions about this contract
Who was awarded the construction contract by Town of Sacred Heart?
GRIDOR was awarded this construction contract by Town of Sacred Heart, as recorded on April 12, 2021.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in city_council_regular_meeting_minutes_april_12_2021.pdf (Minutes), dated April 12, 2021 from Town of Sacred Heart. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does GRIDOR hold?
GRIDOR may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Town of Sacred Heart currently buying?
Explore Town of Sacred Heart's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.