CONSTRUCTIONAMENDED

Water Supply Project Contract Dates Extended

The Ashland City Council approved Change Order No. 2 with General Excavating for the 2025 Water Supply Improvements project, extending substantial completion to July 31, 2026 and final payment readiness to August 31, 2026. The amendment appears to be a schedule change only, with no dollar amount discussed in the minutes.

Status
AMENDED
Document date
July 16, 2026
Contract type
CONSTRUCTION
Vendor
General Excavating
Agency
Town of Ashland · NE

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Substantial Completion Date changed to July 31, 2026; Final Payment Readiness Date changed to August 31, 2026
Renewal date
2026-08-31
Renewal
Change Order No. 2 extends the construction schedule, resetting substantial completion to July 31, 2026 and final payment readiness to August 31, 2026.
Document type
Minutes
Source document
Ashland City Council Regular Meeting Minutes 2026-07-16

Related contracts

Other contracts from General Excavating.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Ashland?

General Excavating was awarded this construction contract by Town of Ashland, as recorded on July 16, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Ashland City Council Regular Meeting Minutes 2026-07-16 (Minutes), dated July 16, 2026 from Town of Ashland. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does General Excavating hold?

General Excavating may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View General Excavating's profile

What is Town of Ashland currently buying?

Explore Town of Ashland's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Ashland's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free