Shelco Bid Evaluated for McLeansville Construction
- Disclosed value
- $6,593,233 total construction budget; $472,233 fee and general conditions total
- From report
- Document date
- Feb 10, 2026
The 30-second brief
TMSA evaluated Shelco's bid for the Triad McLeansville Campus general contractor procurement. Shelco's proposal totaled $6,593,233, including $472,233 for fees and general conditions, but Hubrich was recommended instead.
SHELCO holds this construction contract with The Math And Science Academy Of Apex. Its other public contracts on record include work for City of Arapahoe and Wallace village.
Term as filed: Approximately seven months of construction planned for the Fall 2026 opening.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $6,593,233 total construction budget; $472,233 fee and general conditions total
- Document date
- February 10, 2026
- Term
- Approximately seven months of construction planned for the Fall 2026 opening
- Vendor
- SHELCO
- Source document
- TMSA Public Charter Schools Report General Contractor Selection 2026-02-10 (Report)
SHELCO's other public contracts
More The Math And Science Academy Of Apex contracts
Questions about this contract
Who was awarded the construction contract by The Math And Science Academy Of Apex?
SHELCO was awarded this construction contract by The Math And Science Academy Of Apex, as recorded on February 10, 2026. The contract value is $6,593,233 total construction budget; $472,233 fee and general conditions total.
How much is the SHELCO contract with The Math And Science Academy Of Apex worth?
The SHELCO contract with The Math And Science Academy Of Apex is valued at $6,593,233 total construction budget; $472,233 fee and general conditions total, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in TMSA Public Charter Schools Report General Contractor Selection 2026-02-10 (Report), dated February 10, 2026 from The Math And Science Academy Of Apex. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does SHELCO hold?
SHELCO may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is The Math And Science Academy Of Apex currently buying?
Explore The Math And Science Academy Of Apex's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.