South Coast Water District Awards Construction Contract to Jeremy Harris Construction Inc (August 2026)
- Disclosed value
- Not to exceed $298,942 (original); credits totaling $40,672; final construction contract cost $258,270 within 10% contingency
- From agendapacket
- Approved
- Aug 3, 2026
The 30-second brief
South Coast Water District, acting as Designated Operator for the JRWSS, awarded Jeremy Harris Construction, Inc. a construction contract of up to $298,942 for slope repair and related improvements at Calle Vista Torito, later adjusted by net credit change orders. Work commenced in August 2025 and was completed on November 14, 2025, with staff now recommending filing a Notice of Completion and releasing retention funds.
Jeremy Harris Construction Inc holds this construction contract with South Coast Water District. Its other public contracts on record include work for City of Hesperia and City of Newport Beach.
Term as filed: Construction contract executed August 13, 2025; Notice to Proceed August 21, 2025; work completed November 14, 2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Not to exceed $298,942 (original); credits totaling $40,672; final construction contract cost $258,270 within 10% contingency
- Document date
- August 3, 2026
- Term
- Construction contract executed August 13, 2025; Notice to Proceed August 21, 2025; work completed November 14, 2025
- Source document
- South Coast Water District Engineering & Operations Committee Agenda Packet 2026-08-03 (AgendaPacket)
Jeremy Harris Construction Inc's other public contracts
More South Coast Water District contracts
Questions about this contract
Who was awarded the construction contract by South Coast Water District?
Jeremy Harris Construction Inc was awarded this construction contract by South Coast Water District, as recorded on August 3, 2026. The contract value is Not to exceed $298,942 (original); credits totaling $40,672; final construction contract cost $258,270 within 10% contingency.
How much is the Jeremy Harris Construction Inc contract with South Coast Water District worth?
The Jeremy Harris Construction Inc contract with South Coast Water District is valued at Not to exceed $298,942 (original); credits totaling $40,672; final construction contract cost $258,270 within 10% contingency, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in South Coast Water District Engineering & Operations Committee Agenda Packet 2026-08-03 (AgendaPacket), dated August 3, 2026 from South Coast Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Jeremy Harris Construction Inc hold?
Jeremy Harris Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is South Coast Water District currently buying?
Explore South Coast Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.