Fremont Millwork Change Order Reduces Briarwood Contract
- Disclosed value
- $(42,755.00) deductive change order; revised contract sum $277,645.00
- From contract
- Document date
- Sep 25, 2026
The 30-second brief
Santa Clara Unified School District approved a final deductive change order with Fremont Millwork Co. for the Briarwood Elementary School Modernization project. The change reduces the contract by $42,755.00, lowering the contract sum from $320,400.00 to $277,645.00, with no change to the contract schedule.
Fremont Millwork Company holds this construction contract with Santa Clara Unified. Its other public contracts on record include work for San Mateo County Community College District Office.
Term as filed: Contract time changed by 0 calendar days; substantial completion date unchanged.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $(42,755.00) deductive change order; revised contract sum $277,645.00
- Document date
- September 25, 2026
- Term
- Contract time changed by 0 calendar days; substantial completion date unchanged
- Vendor
- Fremont Millwork Company
- Agency
- Santa Clara Unified
- Source document
- Santa Clara Unified School District Contract Change Order Briarwood ES Modernization 2026-09-25 (Contract)
Fremont Millwork Company's other public contracts
More Santa Clara Unified contracts
Questions about this contract
Who was awarded the construction contract by Santa Clara Unified?
Fremont Millwork Company was awarded this construction contract by Santa Clara Unified, as recorded on September 25, 2026. The contract value is $(42,755.00) deductive change order; revised contract sum $277,645.00.
How much is the Fremont Millwork Company contract with Santa Clara Unified worth?
The Fremont Millwork Company contract with Santa Clara Unified is valued at $(42,755.00) deductive change order; revised contract sum $277,645.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Santa Clara Unified School District Contract Change Order Briarwood ES Modernization 2026-09-25 (Contract), dated September 25, 2026 from Santa Clara Unified. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Fremont Millwork Company hold?
Fremont Millwork Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Santa Clara Unified currently buying?
Explore Santa Clara Unified's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.