CONTRACTAMENDED

Mountain Tunnel improvements contract contingency increased by $15M

San Francisco Public Utilities Commission logoSan Francisco Public Utilities Commission
Disclosed value
Revised cost limit $165,173,126 (increase of $15,000,000)
From resolution
Document date
Jul 29, 2026
Term
No change to contract duration limit

The 30-second brief

What it covers

The SFPUC raised the cost limit on Mountain Tunnel Constructors, Inc.’s HH-1000R Mountain Tunnel Improvements project by $15 million to $165,173,126, maintaining the existing schedule. The added contingency funds schedule disruptions and design changes.

Who holds it

Mountain Tunnel Constructors Inc holds this construction contract with San Francisco Public Utilities Commission.

What happens next

Term as filed: No change to contract duration limit.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Revised cost limit $165,173,126 (increase of $15,000,000)
Document date
July 29, 2026
Term
No change to contract duration limit
Source document
SFPUC Resolution Log 2026-07-29 (Resolution)

Mountain Tunnel Constructors Inc's other public contracts

More San Francisco Public Utilities Commission contracts

Questions about this contract

Who was awarded the construction contract by San Francisco Public Utilities Commission?

Mountain Tunnel Constructors Inc was awarded this construction contract by San Francisco Public Utilities Commission, as recorded on July 29, 2026. The contract value is Revised cost limit $165,173,126 (increase of $15,000,000).

How much is the Mountain Tunnel Constructors Inc contract with San Francisco Public Utilities Commission worth?

The Mountain Tunnel Constructors Inc contract with San Francisco Public Utilities Commission is valued at Revised cost limit $165,173,126 (increase of $15,000,000), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a resolution record.

Where was this contract approved?

This contract appears in SFPUC Resolution Log 2026-07-29 (Resolution), dated July 29, 2026 from San Francisco Public Utilities Commission. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Mountain Tunnel Constructors Inc hold?

Mountain Tunnel Constructors Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is San Francisco Public Utilities Commission currently buying?

Explore San Francisco Public Utilities Commission's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →