CONTRACTAPPROVED

RM of St. Clements Awards Construction Contract to Waterside Development Corporation (July 2026)

RM of St. Clements logoRM of St. Clements
Disclosed value
$8,152,475.00 (of total project cost approx. $14 million; federal funding $5.875 million secured)
From minutes
Approved
Jul 14, 2026
Renews
Free account

The 30-second brief

What it covers

The RM of St. Clements Council approved a Construction Letter of Intent with Waterside Development Corporation for a regional wastewater treatment upgrade project, estimated at approximately $14 million with $5.875 million in federal funding secured. Work is targeted to begin in January 2027 and reach substantial completion by September 2027, including upgrades to the existing lagoon and a new outfall pipeline to the Red River.

Who holds it

Waterside Development Corporation holds this construction contract with RM of St. Clements.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every RM of St. Clements contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$8,152,475.00 (of total project cost approx. $14 million; federal funding $5.875 million secured)
Document date
July 14, 2026
Term
Construction targeted to begin January 2027 with likely substantial completion by September 2027
Renews
Free account
Source document
RM of St. Clements Minutes Special Meeting of Council 2026-07-14 (Minutes)

More RM of St. Clements contracts

Questions about this contract

Who was awarded the construction contract by RM of St. Clements?

Waterside Development Corporation was awarded this construction contract by RM of St. Clements, as recorded on July 14, 2026. The contract value is $8,152,475.00 (of total project cost approx. $14 million; federal funding $5.875 million secured).

How much is the Waterside Development Corporation contract with RM of St. Clements worth?

The Waterside Development Corporation contract with RM of St. Clements is valued at $8,152,475.00 (of total project cost approx. $14 million; federal funding $5.875 million secured), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in RM of St. Clements Minutes Special Meeting of Council 2026-07-14 (Minutes), dated July 14, 2026 from RM of St. Clements. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Waterside Development Corporation hold?

Waterside Development Corporation may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is RM of St. Clements currently buying?

Explore RM of St. Clements's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →