CONTRACTONGOING

Lynch Completes Newport Pell Tolling Corridor Contract

Rhode Island Turnpike and Bridge Authority | State of Rhode Island logoRhode Island Turnpike and Bridge Authority | State of Rhode Island
Disclosed value
$13,759,843 revised project budget for the Phase II AET project
From agendapacket
Document date
Jun 11, 2025

The 30-second brief

What it covers

Lynch was the contractor for RITBA’s Phase II AET Newport Pell Bridge tolling corridor project. The project is 100% complete, with only minor punch-list work remaining, against an original contract amount of $10,759,843.

Who holds it

LYNCH holds this construction contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island. Its other public contracts on record include work for Town of East Troy and Grafton School District.

What happens next

Term as filed: Project complete; minor punch list remaining.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$13,759,843 revised project budget for the Phase II AET project
Document date
June 11, 2025
Term
Project complete; minor punch list remaining
Vendor
LYNCH
Source document
Rhode Island Turnpike and Bridge Authority AgendaPacket Board Meeting June 11, 2025 (AgendaPacket)

LYNCH's other public contracts

More Rhode Island Turnpike and Bridge Authority | State of Rhode Island contracts

Questions about this contract

Who was awarded the construction contract by Rhode Island Turnpike and Bridge Authority | State of Rhode Island?

LYNCH was awarded this construction contract by Rhode Island Turnpike and Bridge Authority | State of Rhode Island, as recorded on June 11, 2025. The contract value is $13,759,843 revised project budget for the Phase II AET project.

How much is the LYNCH contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island worth?

The LYNCH contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island is valued at $13,759,843 revised project budget for the Phase II AET project, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Rhode Island Turnpike and Bridge Authority AgendaPacket Board Meeting June 11, 2025 (AgendaPacket), dated June 11, 2025 from Rhode Island Turnpike and Bridge Authority | State of Rhode Island. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does LYNCH hold?

LYNCH may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Rhode Island Turnpike and Bridge Authority | State of Rhode Island currently buying?

Explore Rhode Island Turnpike and Bridge Authority | State of Rhode Island's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →