District Recommends $1.28 Million Levee Progress Payment

Reclamation District 1601
Disclosed value
Net payment due $1,279,830.12; current earnings $1,347,189.60 less 5% retention of $67,359.48
From report
Document date
Sep 15, 2026

The 30-second brief

What it covers

Reclamation District No. 1601 recommended a $1,279,830.12 progress payment to The Dutra Group for Reach 6 Phase 1 setback levee work completed through August 31, 2026. The payment reflects 5% retention, bringing cumulative net earnings to $5.23 million.

Who holds it

The Dutra Group holds this construction contract with Reclamation District 1601. Its other public contracts on record include work for City of Berkeley and Canaveral Port District.

What happens next

Term as filed: Progress through August 31, 2026; Progress Pay Estimate No. 4 dated September 8, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Net payment due $1,279,830.12; current earnings $1,347,189.60 less 5% retention of $67,359.48
Document date
September 15, 2026
Term
Progress through August 31, 2026; Progress Pay Estimate No. 4 dated September 8, 2026
Source document
Reclamation District No. 1601 - Twitchell Island Engineer's Report 2026-09-15 (Report)

The Dutra Group's other public contracts

More Reclamation District 1601 contracts

Questions about this contract

Who was awarded the construction contract by Reclamation District 1601?

The Dutra Group was awarded this construction contract by Reclamation District 1601, as recorded on September 15, 2026. The contract value is Net payment due $1,279,830.12; current earnings $1,347,189.60 less 5% retention of $67,359.48.

How much is the The Dutra Group contract with Reclamation District 1601 worth?

The The Dutra Group contract with Reclamation District 1601 is valued at Net payment due $1,279,830.12; current earnings $1,347,189.60 less 5% retention of $67,359.48, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Reclamation District No. 1601 - Twitchell Island Engineer's Report 2026-09-15 (Report), dated September 15, 2026 from Reclamation District 1601. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does The Dutra Group hold?

The Dutra Group may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Reclamation District 1601 currently buying?

Explore Reclamation District 1601's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →