Change order extends school security project schedule
- Disclosed value
- $378,593.00 (no change in sum for this Change Order)
- From contract
- Document date
- Mar 2, 2026
The 30-second brief
Rapides Parish School Board issued Change Order 001 to Chart Construction LLC for the Rapides High School Safety and Security Project, extending the contract time by 65 days with no change to the $378,593 contract sum. The new substantial completion date is April 23, 2026 to account for weather and fencing delays.
Chart Construction LLC holds this construction contract with Rapides Parish School District. Its other public contracts on record include work for St. Martin Parish and Iberia Parish School District.
Term as filed: Original contract date September 08, 2025; Contract Time increased by 65 days; new Substantial Completion date April 23, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $378,593.00 (no change in sum for this Change Order)
- Document date
- March 2, 2026
- Term
- Original contract date September 08, 2025; Contract Time increased by 65 days; new Substantial Completion date April 23, 2026
- Vendor
- Chart Construction LLC
- Source document
- Rapides Parish School Board Change Order 001 2026-03-02 (Contract)
Chart Construction LLC's other public contracts
More Rapides Parish School District contracts
Questions about this contract
Who was awarded the construction contract by Rapides Parish School District?
Chart Construction LLC was awarded this construction contract by Rapides Parish School District, as recorded on March 2, 2026. The contract value is $378,593.00 (no change in sum for this Change Order).
How much is the Chart Construction LLC contract with Rapides Parish School District worth?
The Chart Construction LLC contract with Rapides Parish School District is valued at $378,593.00 (no change in sum for this Change Order), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Rapides Parish School Board Change Order 001 2026-03-02 (Contract), dated March 2, 2026 from Rapides Parish School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Chart Construction LLC hold?
Chart Construction LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Rapides Parish School District currently buying?
Explore Rapides Parish School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.