Roadway Sign Rehab Change Order Approved with DPR
- Disclosed value
- $842,066.13 (change order; new GMP total $23,227,224.63)
- From minutes
- Document date
- Nov 21, 2019
- Term
- Contract time extended 104 calendar days
The 30-second brief
The Raleigh-Durham Airport Authority approved Change Order No. 2 with DPR Construction for the Roadway Informational Sign Rehabilitation Project, adding $842,066.13 and extending the contract by 104 days. The amendment supports larger and additional signs for Park Express and new air service, bringing the Landside Civil Package GMP to $23,227,224.63.
Dpr Construction holds this construction contract with Raleigh-Durham Airport Authority. Its other public contracts on record include work for San Diego Community College District-District Office and Comptroller of Maryland|Office of the Comptroller.
Term as filed: Contract time extended 104 calendar days.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $842,066.13 (change order; new GMP total $23,227,224.63)
- Document date
- November 21, 2019
- Term
- Contract time extended 104 calendar days
- Vendor
- Dpr Construction
- Source document
- raleigh-durham-airport-authority-board-meeting-minutes-november-21-2019_d9a.pdf (Minutes)
Dpr Construction's other public contracts
More Raleigh-Durham Airport Authority contracts
Questions about this contract
Who was awarded the construction contract by Raleigh-Durham Airport Authority?
Dpr Construction was awarded this construction contract by Raleigh-Durham Airport Authority, as recorded on November 21, 2019. The contract value is $842,066.13 (change order; new GMP total $23,227,224.63).
How much is the Dpr Construction contract with Raleigh-Durham Airport Authority worth?
The Dpr Construction contract with Raleigh-Durham Airport Authority is valued at $842,066.13 (change order; new GMP total $23,227,224.63), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in raleigh-durham-airport-authority-board-meeting-minutes-november-21-2019_d9a.pdf (Minutes), dated November 21, 2019 from Raleigh-Durham Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Dpr Construction hold?
Dpr Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Raleigh-Durham Airport Authority currently buying?
Explore Raleigh-Durham Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.