CONTRACTAMENDED

Final change order approved for Pier E gate project

Port of Long Beach logoPort of Long Beach
Disclosed value
Net credit amount of ($268,641.95), including additive changes of $223,757.76 and deductive changes of ($492,399.71); revised total contract amount $12,733,626.65
From staffreport
Document date
Jul 26, 2026

The 30-second brief

What it covers

The Port of Long Beach is authorizing Change Order No. 4 to its construction contract with Reyes Construction Inc. for the Pier E North Gate Expansion project, resulting in a net credit of $268,641.95 and a revised contract total of $12,733,626.65. This final change order adjusts prior quantities and includes striping, electrical, and concrete modifications as the project approaches final acceptance.

Who holds it

Reyes Construction Inc holds this construction contract with Port of Long Beach. Its other public contracts on record include work for San Diego Association of Governments and City of Norwalk.

What happens next

Term as filed: Contract HD-25-0170; Notice-to-Proceed issued May 12, 2025; Substantial Completion revised to June 2, 2026 and Affidavit of Final Completion date to August 1, 2026.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Net credit amount of ($268,641.95), including additive changes of $223,757.76 and deductive changes of ($492,399.71); revised total contract amount $12,733,626.65
Document date
July 26, 2026
Term
Contract HD-25-0170; Notice-to-Proceed issued May 12, 2025; Substantial Completion revised to June 2, 2026 and Affidavit of Final Completion date to August 1, 2026
Source document
Port of Long Beach StaffReport Middle Harbor Terminal Redevelopment Program Pier E North Gate Expansion 2026-07-27 (StaffReport)

Reyes Construction Inc's other public contracts

More Port of Long Beach contracts

Questions about this contract

Who was awarded the construction contract by Port of Long Beach?

Reyes Construction Inc was awarded this construction contract by Port of Long Beach, as recorded on July 26, 2026. The contract value is Net credit amount of ($268,641.95), including additive changes of $223,757.76 and deductive changes of ($492,399.71); revised total contract amount $12,733,626.65.

How much is the Reyes Construction Inc contract with Port of Long Beach worth?

The Reyes Construction Inc contract with Port of Long Beach is valued at Net credit amount of ($268,641.95), including additive changes of $223,757.76 and deductive changes of ($492,399.71); revised total contract amount $12,733,626.65, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Port of Long Beach StaffReport Middle Harbor Terminal Redevelopment Program Pier E North Gate Expansion 2026-07-27 (StaffReport), dated July 26, 2026 from Port of Long Beach. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Reyes Construction Inc hold?

Reyes Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Port of Long Beach currently buying?

Explore Port of Long Beach's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →