HunTel Fiber Proposal Rejected as Non-Responsive
- Disclosed value
- $3,208,038.95 for Route Option 1; $3,113,807.39 for Route Option 2; $6,321,846.34 combined
- From resolution
- Document date
- Oct 13, 2026
- Term
- No guaranteed completion date provided
The 30-second brief
HunTel Engineering, Inc. submitted a proposal for OPPD's Cass to Nebraska City fiber project but was deemed legally non-responsive because it provided no guaranteed completion date. OPPD awarded the project to Bauer Underground Inc.
Huntel Engineering Inc holds this construction contract with Omaha Public Power District.
Term as filed: No guaranteed completion date provided.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $3,208,038.95 for Route Option 1; $3,113,807.39 for Route Option 2; $6,321,846.34 combined
- Document date
- October 13, 2026
- Term
- No guaranteed completion date provided
- Vendor
- Huntel Engineering Inc
- Source document
- Omaha Public Power District Resolution Award RFP No. 6252 – Cass County to Nebraska City Fiber Requirement 2026-10-13 (Resolution)
More Omaha Public Power District contracts
Questions about this contract
Who was awarded the construction contract by Omaha Public Power District?
Huntel Engineering Inc was awarded this construction contract by Omaha Public Power District, as recorded on October 13, 2026. The contract value is $3,208,038.95 for Route Option 1; $3,113,807.39 for Route Option 2; $6,321,846.34 combined.
How much is the Huntel Engineering Inc contract with Omaha Public Power District worth?
The Huntel Engineering Inc contract with Omaha Public Power District is valued at $3,208,038.95 for Route Option 1; $3,113,807.39 for Route Option 2; $6,321,846.34 combined, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a resolution record.
Where was this contract approved?
This contract appears in Omaha Public Power District Resolution Award RFP No. 6252 – Cass County to Nebraska City Fiber Requirement 2026-10-13 (Resolution), dated October 13, 2026 from Omaha Public Power District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Huntel Engineering Inc hold?
Huntel Engineering Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Omaha Public Power District currently buying?
Explore Omaha Public Power District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.