Borbon Painting Contract Reduced by $11,000
- Disclosed value
- ($11,000.00); new contract sum $198,500.00
- From staffreport
- Document date
- Dec 17, 2025
- Term
- 0 days added
The 30-second brief
Mt. San Antonio College approved a $11,000 deduction from Borbon, Incorporated's painting contract for the Building 2 Roof Soffit Replacement and ADA Upgrades Project. The change order removed an unused allowance and reduced the contract total to $198,500 with no time extension.
Borbon Incorporated holds this construction contract with Mt San Antonio College. Its other public contracts on record include work for College Of The Desert.
Term as filed: 0 days added.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- ($11,000.00); new contract sum $198,500.00
- Document date
- December 17, 2025
- Term
- 0 days added
- Vendor
- Borbon Incorporated
- Agency
- Mt San Antonio College
- Source document
- Mt San Antonio College StaffReport Change Order - Borbon Incorporated, Courtney, Inc., K.A.R. Construction, Inc., and RVH Constructors, Inc. (Bid No. 2024-092) for the Building 2 Roof Soffit Replacement and ADA Upgrades Project 2025-12-17 (StaffReport)
Borbon Incorporated's other public contracts
More Mt San Antonio College contracts
Questions about this contract
Who was awarded the construction contract by Mt San Antonio College?
Borbon Incorporated was awarded this construction contract by Mt San Antonio College, as recorded on December 17, 2025. The contract value is ($11,000.00); new contract sum $198,500.00.
How much is the Borbon Incorporated contract with Mt San Antonio College worth?
The Borbon Incorporated contract with Mt San Antonio College is valued at ($11,000.00); new contract sum $198,500.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Mt San Antonio College StaffReport Change Order - Borbon Incorporated, Courtney, Inc., K.A.R. Construction, Inc., and RVH Constructors, Inc. (Bid No. 2024-092) for the Building 2 Roof Soffit Replacement and ADA Upgrades Project 2025-12-17 (StaffReport), dated December 17, 2025 from Mt San Antonio College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Borbon Incorporated hold?
Borbon Incorporated may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Mt San Antonio College currently buying?
Explore Mt San Antonio College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.