Louisville Regional Airport Authority Awards Maintenance Contract to WINLECTRIC (July 2026)
- Disclosed value
- $250,000 preliminary total project estimate, including $226,468.50 for inspection, parts, and materials
- From minutes
- Approved
- Jul 15, 2026
The 30-second brief
The Louisville Regional Airport Authority approved an emergency procurement through Winlectric for repairs to the airport's alternate power switchgear. The preliminary project estimate is $250,000, including parts, materials, inspection, and labor.
WINLECTRIC holds this maintenance contract with Louisville Regional Airport Authority. Its other public contracts on record include work for Town of Marion and Newport Independent School District.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Maintenance
- Amount
- $250,000 preliminary total project estimate, including $226,468.50 for inspection, parts, and materials
- Document date
- July 15, 2026
- Vendor
- WINLECTRIC
- Source document
- Louisville Regional Airport Authority Minutes Board Meeting July 15, 2026 (Minutes)
WINLECTRIC's other public contracts
More Louisville Regional Airport Authority contracts
Questions about this contract
Who was awarded the maintenance contract by Louisville Regional Airport Authority?
WINLECTRIC was awarded this maintenance contract by Louisville Regional Airport Authority, as recorded on July 15, 2026. The contract value is $250,000 preliminary total project estimate, including $226,468.50 for inspection, parts, and materials.
How much is the WINLECTRIC contract with Louisville Regional Airport Authority worth?
The WINLECTRIC contract with Louisville Regional Airport Authority is valued at $250,000 preliminary total project estimate, including $226,468.50 for inspection, parts, and materials, covering maintenance work.
What type of contract is this?
This is a Maintenance contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Louisville Regional Airport Authority Minutes Board Meeting July 15, 2026 (Minutes), dated July 15, 2026 from Louisville Regional Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does WINLECTRIC hold?
WINLECTRIC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Louisville Regional Airport Authority currently buying?
Explore Louisville Regional Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.