Lodi Unified Approves Final Mosher School Change Order
- Disclosed value
- Total change orders amount: $135,500.00; Final contract price: $1,490,500.00
- From contract
- Document date
- Jan 20, 2026
The 30-second brief
Lodi Unified School District authorized a final $135,500.00 change order with AM Stephens Construction Co., Inc. for the Mosher Elementary School Portable Classroom & Play Yard Project. The allowance adjustment offsets the change order, resulting in a final contract price of $1,490,500.00.
Am Stephens Construction Co Inc holds this construction contract with Lodi Unified. Its other public contracts on record include work for Aspire Stockton 6-12 Secondary Academy District and Stockton Collegiate International Secondary District.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Total change orders amount: $135,500.00; Final contract price: $1,490,500.00
- Document date
- January 20, 2026
- Agency
- Lodi Unified
- Source document
- Lodi Unified School District Contract Final Change Order Mosher Elementary School Portable Classroom & Play Yard Project 2026-01-20 (Contract)
Am Stephens Construction Co Inc's other public contracts
More Lodi Unified contracts
Questions about this contract
Who was awarded the construction contract by Lodi Unified?
Am Stephens Construction Co Inc was awarded this construction contract by Lodi Unified, as recorded on January 20, 2026. The contract value is Total change orders amount: $135,500.00; Final contract price: $1,490,500.00.
How much is the Am Stephens Construction Co Inc contract with Lodi Unified worth?
The Am Stephens Construction Co Inc contract with Lodi Unified is valued at Total change orders amount: $135,500.00; Final contract price: $1,490,500.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Lodi Unified School District Contract Final Change Order Mosher Elementary School Portable Classroom & Play Yard Project 2026-01-20 (Contract), dated January 20, 2026 from Lodi Unified. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Am Stephens Construction Co Inc hold?
Am Stephens Construction Co Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Lodi Unified currently buying?
Explore Lodi Unified's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.