CONTRACTAMENDED

Library to Assess Liquidated Damages on T-Built

Licking County Library logoLicking County Library
Document date
Nov 19, 2025

The 30-second brief

What it covers

The Licking County Library Board voted to proceed with assessing liquidated damages against T-Built Construction under its construction contract. The Board will enforce the agreement’s liquidated damages clause based on a substantial completion date of September 5, 2025.

Who holds it

T-built Construction holds this construction contract with Licking County Library. Its other public contracts on record include work for LICKING COUNTY LIBRARY.

What happens next

Term as filed: Substantial completion date of September 5, 2025 referenced.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
November 19, 2025
Term
Substantial completion date of September 5, 2025 referenced
Vendor
T-built Construction
Source document
Licking County Library Minutes Regular Business Meeting 2025-11-19 (Minutes)

T-built Construction's other public contracts

More Licking County Library contracts

Questions about this contract

Who was awarded the construction contract by Licking County Library?

T-built Construction was awarded this construction contract by Licking County Library, as recorded on November 19, 2025.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Licking County Library Minutes Regular Business Meeting 2025-11-19 (Minutes), dated November 19, 2025 from Licking County Library. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What is Licking County Library currently buying?

Explore Licking County Library's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →