- Disclosed value
- $1,323,126.45 original; $72,509.37 CO #1; $127,842.12 CO #2; ($99,684.44) CO #3; final revised contract $1,423,793.50; final payment (retainage) $71,189.67
- From report
- Approved
- Dec 19, 2025
The 30-second brief
The School Board of Lee County approved a continuing construction management contract with Wright Construction Group, Inc. for the Lehigh Senior High School Painting Project under RFQ CQ24-0121LN. The original contract of $1,323,126.45 was adjusted through three change orders to a final amount of $1,423,793.50, and staff now recommend releasing the final retainage payment of $71,189.67 following project closeout review. Bonding, insurance, and payment applications were reviewed and verified by Risk Management and Internal Compliance.
Wright Construction Group Inc holds this construction contract with Lee County School District. Its other public contracts on record include work for Lee County School District - Procurement Services and Collier County.
Term as filed: Contract dated December 9, 2024; work began April 2025; Performance & Payment Bond dated December 19, 2024 and recorded January 29, 2025; Consent of Surety to Final Payment dated September 30, 2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $1,323,126.45 original; $72,509.37 CO #1; $127,842.12 CO #2; ($99,684.44) CO #3; final revised contract $1,423,793.50; final payment (retainage) $71,189.67
- Document date
- December 19, 2025
- Term
- Contract dated December 9, 2024; work began April 2025; Performance & Payment Bond dated December 19, 2024 and recorded January 29, 2025; Consent of Surety to Final Payment dated September 30, 2025
- Source document
- The School District of Lee County Report Lehigh Senior High School Painting Project Review 2025-12-19 (Report)
Wright Construction Group Inc's other public contracts
More Lee County School District contracts
Questions about this contract
Who was awarded the construction contract by Lee County School District?
Wright Construction Group Inc was awarded this construction contract by Lee County School District, as recorded on December 19, 2025. The contract value is $1,323,126.45 original; $72,509.37 CO #1; $127,842.12 CO #2; ($99,684.44) CO #3; final revised contract $1,423,793.50; final payment (retainage) $71,189.67.
How much is the Wright Construction Group Inc contract with Lee County School District worth?
The Wright Construction Group Inc contract with Lee County School District is valued at $1,323,126.45 original; $72,509.37 CO #1; $127,842.12 CO #2; ($99,684.44) CO #3; final revised contract $1,423,793.50; final payment (retainage) $71,189.67, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in The School District of Lee County Report Lehigh Senior High School Painting Project Review 2025-12-19 (Report), dated December 19, 2025 from Lee County School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Wright Construction Group Inc hold?
Wright Construction Group Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Lee County School District currently buying?
Explore Lee County School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.