Lake Arthur Bond Change Order Adds 38 Days
- Disclosed value
- $0.00; cumulative contract sum remains $4,134,028.00
- From agenda
- Document date
- Oct 15, 2026
- Renews
- Free account
The 30-second brief
Jefferson Davis Parish School Board is considering accepting Change Order No. 4 from Pat Williams Construction for the Lake Arthur Bond project. The change order adds 38 days at no additional cost and moves substantial completion to October 29, 2026.
Pat Williams Construction holds this construction contract with Jefferson Davis Parish School District. Its other public contracts on record include work for Beauregard Parish School District and Rapides Parish School District.
The renewal date is on record. A free account shows it, with the renewals for every Jefferson Davis Parish School District contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $0.00; cumulative contract sum remains $4,134,028.00
- Document date
- October 15, 2026
- Term
- Contract time increased by 38 days; new substantial completion date October 29, 2026
- Renews
- Free account
- Source document
- Jefferson Davis Parish School Board Agenda 2026-10-15 (Agenda)
Pat Williams Construction's other public contracts
More Jefferson Davis Parish School District contracts
Questions about this contract
Who was awarded the construction contract by Jefferson Davis Parish School District?
Pat Williams Construction was awarded this construction contract by Jefferson Davis Parish School District, as recorded on October 15, 2026. The contract value is $0.00; cumulative contract sum remains $4,134,028.00.
How much is the Pat Williams Construction contract with Jefferson Davis Parish School District worth?
The Pat Williams Construction contract with Jefferson Davis Parish School District is valued at $0.00; cumulative contract sum remains $4,134,028.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Jefferson Davis Parish School Board Agenda 2026-10-15 (Agenda), dated October 15, 2026 from Jefferson Davis Parish School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Pat Williams Construction hold?
Pat Williams Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Jefferson Davis Parish School District currently buying?
Explore Jefferson Davis Parish School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.