Burbank Water and Power Advances Terminal Substation Work

Hollywood Burbank Airport Authority
Disclosed value
$19,670,093 current design-build deposit; total projected power infrastructure cost $70,253,937
From agendapacket
Document date
Sep 8, 2026

The 30-second brief

What it covers

Burbank Water and Power is continuing work to provide permanent power for the Replacement Passenger Terminal under the executed Electrical Service Agreement. The Authority’s current $19.67 million deposit supports a community substation expected to be completed in 2028 or 2029.

Who holds it

Burbank Water & Power holds this utilities contract with Hollywood Burbank Airport Authority. Its other public contracts on record include work for Burbank-Glendale-Pasadena Airport Auth and Burbank-Glendale-Pasadena Airport Authority.

What happens next

Term as filed: Permanent substation expected to be completed and energized in 2028/2029.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Utilities
Amount
$19,670,093 current design-build deposit; total projected power infrastructure cost $70,253,937
Document date
September 8, 2026
Term
Permanent substation expected to be completed and energized in 2028/2029
Vendor
Burbank Water & Power
Source document
Burbank-Glendale-Pasadena Airport Authority AgendaPacket Special Meeting September 8, 2026 (AgendaPacket)

Burbank Water & Power's other public contracts

More Hollywood Burbank Airport Authority contracts

Questions about this contract

Who was awarded the utilities contract by Hollywood Burbank Airport Authority?

Burbank Water & Power was awarded this utilities contract by Hollywood Burbank Airport Authority, as recorded on September 8, 2026. The contract value is $19,670,093 current design-build deposit; total projected power infrastructure cost $70,253,937.

How much is the Burbank Water & Power contract with Hollywood Burbank Airport Authority worth?

The Burbank Water & Power contract with Hollywood Burbank Airport Authority is valued at $19,670,093 current design-build deposit; total projected power infrastructure cost $70,253,937, covering utilities work.

What type of contract is this?

This is a Utilities contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Burbank-Glendale-Pasadena Airport Authority AgendaPacket Special Meeting September 8, 2026 (AgendaPacket), dated September 8, 2026 from Hollywood Burbank Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is Hollywood Burbank Airport Authority currently buying?

Explore Hollywood Burbank Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →