District Considers Sukut Wastewater Change Order
- Disclosed value
- $178,348.00 incremental change order; revised contract amount $75,153,279.44
- From agendapacket
- Document date
- Oct 20, 2026
- Renews
- Free account
The 30-second brief
Hi-Desert Water District is considering a $178,348 change order for Sukut Construction, LLC on the Phase II Wastewater Collection System Project. The work adds 90% design and utility potholing for the Alternate Contingent Area while leaving the December 30, 2026 completion date unchanged.
Sukut Construction LLC holds this construction contract with Hi-Desert Water District. Its other public contracts on record include work for Elsinore Valley Municipal Water District and City of Redlands.
The renewal date is on record. A free account shows it, with the renewals for every Hi-Desert Water District contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $178,348.00 incremental change order; revised contract amount $75,153,279.44
- Document date
- October 20, 2026
- Term
- Construction notice to proceed July 15, 2025; contract completion December 30, 2026; revised completion date December 30, 2026
- Renews
- Free account
- Vendor
- Sukut Construction LLC
- Agency
- Hi-Desert Water District
- Source document
- Hi-Desert Water District AgendaPacket Regular Board Meeting Agenda 2026-10-21 (AgendaPacket)
Sukut Construction LLC's other public contracts
More Hi-Desert Water District contracts
Questions about this contract
Who was awarded the construction contract by Hi-Desert Water District?
Sukut Construction LLC was awarded this construction contract by Hi-Desert Water District, as recorded on October 20, 2026. The contract value is $178,348.00 incremental change order; revised contract amount $75,153,279.44.
How much is the Sukut Construction LLC contract with Hi-Desert Water District worth?
The Sukut Construction LLC contract with Hi-Desert Water District is valued at $178,348.00 incremental change order; revised contract amount $75,153,279.44, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Hi-Desert Water District AgendaPacket Regular Board Meeting Agenda 2026-10-21 (AgendaPacket), dated October 20, 2026 from Hi-Desert Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Sukut Construction LLC hold?
Sukut Construction LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Hi-Desert Water District currently buying?
Explore Hi-Desert Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.