Greer Middle College Approves $100,000 J Davis Change Order
Greer Middle College Charter HighSchool · Taylors, SC- Disclosed value
- $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal
- From minutes
- Document date
- Apr 27, 2026
The 30-second brief
Greer Middle College approved a $100,000 lump-sum payment to J Davis Construction for construction overages, change orders, and topsoil removal costs. The work included field facilities, roadway construction, a required traffic-light loop, and a fieldhouse expansion under a guaranteed maximum price contract.
J Davis Construction holds this construction contract with Greer Middle College Charter High. Its other public contracts on record include work for Town of Hulbert and City of Goose Creek.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal
- Document date
- April 27, 2026
- Vendor
- J Davis Construction
- Source document
- Greer Middle College Charter High School Board of Directors Meeting Minutes 2026-04-27 (Minutes)
J Davis Construction's other public contracts
More Greer Middle College Charter High contracts
Questions about this contract
Who was awarded the construction contract by Greer Middle College Charter High?
J Davis Construction was awarded this construction contract by Greer Middle College Charter High, as recorded on April 27, 2026. The contract value is $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal.
How much is the J Davis Construction contract with Greer Middle College Charter High worth?
The J Davis Construction contract with Greer Middle College Charter High is valued at $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Greer Middle College Charter High School Board of Directors Meeting Minutes 2026-04-27 (Minutes), dated April 27, 2026 from Greer Middle College Charter High. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does J Davis Construction hold?
J Davis Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Greer Middle College Charter High currently buying?