CONTRACTAMENDED

Greer Middle College Approves $100,000 J Davis Change Order

Greer Middle College Charter High
Disclosed value
$100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal
From minutes
Document date
Apr 27, 2026

The 30-second brief

What it covers

Greer Middle College approved a $100,000 lump-sum payment to J Davis Construction for construction overages, change orders, and topsoil removal costs. The work included field facilities, roadway construction, a required traffic-light loop, and a fieldhouse expansion under a guaranteed maximum price contract.

Who holds it

J Davis Construction holds this construction contract with Greer Middle College Charter High. Its other public contracts on record include work for Town of Hulbert and City of Goose Creek.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal
Document date
April 27, 2026
Source document
Greer Middle College Charter High School Board of Directors Meeting Minutes 2026-04-27 (Minutes)

J Davis Construction's other public contracts

More Greer Middle College Charter High contracts

Questions about this contract

Who was awarded the construction contract by Greer Middle College Charter High?

J Davis Construction was awarded this construction contract by Greer Middle College Charter High, as recorded on April 27, 2026. The contract value is $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal.

How much is the J Davis Construction contract with Greer Middle College Charter High worth?

The J Davis Construction contract with Greer Middle College Charter High is valued at $100,000.00 lump sum; identified overages included $45,000.00 for the field facilities building, $30,000.00 for roadway construction, and $25,00.00 for topsoil overage and removal, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Greer Middle College Charter High School Board of Directors Meeting Minutes 2026-04-27 (Minutes), dated April 27, 2026 from Greer Middle College Charter High. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does J Davis Construction hold?

J Davis Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Greer Middle College Charter High currently buying?

Explore Greer Middle College Charter High's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.