Phase II Maintenance Facility Contract Progress With Halme
- Disclosed value
- $7,587,107 (current contract; original $7,425,000; net change by change order $162,107)
- From report
- Document date
- Jun 1, 2026
The 30-second brief
Grant Transit Authority continues its Phase II Maintenance Facility construction with Halme Builders under a contract now totaling $7,587,107 after nine change orders. The project reached substantial completion in April 2026, with punch list work underway and charging island completion scheduled for July 23, 2026.
Halme Builders holds this construction contract with Grant Transit Authority. Its other public contracts on record include work for Methow Valley School District and Lincoln County.
Term as filed: 7/23/2024 – 11/30/2025 (contract completion date); substantial completion 4/2/2026; punch list 6/17/2026; scheduled charging island completion 7/23/2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $7,587,107 (current contract; original $7,425,000; net change by change order $162,107)
- Document date
- June 1, 2026
- Term
- 7/23/2024 – 11/30/2025 (contract completion date); substantial completion 4/2/2026; punch list 6/17/2026; scheduled charging island completion 7/23/2026
- Vendor
- Halme Builders
- Agency
- Grant Transit Authority
- Source document
- Grant Transit Authority General Managers Report June 2026 (Report)
Halme Builders's other public contracts
More Grant Transit Authority contracts
Questions about this contract
Who was awarded the construction contract by Grant Transit Authority?
Halme Builders was awarded this construction contract by Grant Transit Authority, as recorded on June 1, 2026. The contract value is $7,587,107 (current contract; original $7,425,000; net change by change order $162,107).
How much is the Halme Builders contract with Grant Transit Authority worth?
The Halme Builders contract with Grant Transit Authority is valued at $7,587,107 (current contract; original $7,425,000; net change by change order $162,107), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Grant Transit Authority General Managers Report June 2026 (Report), dated June 1, 2026 from Grant Transit Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Halme Builders hold?
Halme Builders may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Grant Transit Authority currently buying?
Explore Grant Transit Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.