Granada Community Services District Awards Construction Contract to Sewer Authority Mid-coastside (August 2026)

Granada Community Services District approved an amended Sewer Authority Mid-Coastside FY 2026/27 budget to fund the $13.23 million progressive design-build contract with McGuire Hester for the Montara force main replacement, raising the project’s total estimated cost to about $16.5 million. The decision locks in GCSD’s roughly 18.21% share of the expanded budget and supports project completion by June 30, 2028.

Status
APPROVED
Document date
August 17, 2026
Contract type
CONSTRUCTION
Vendor
Sewer Authority Mid-coastside
Agency
Granada Community Services District · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$13,228,000 (GMP for construction contract with McGuire Hester); total Option 2 project cost estimated at $16,486,938; GCSD FY 2026/27 share $2,212,515–$2,321,775 depending on table referenced
Contract type
CONSTRUCTION
Contract term
Project completion by June 30, 2028 under Option 2 schedule
Renewal date
2028-06-30
Renewal
This action amends and increases the previously approved SAM FY 2026/27 General Budget infrastructure allocation for the Montara Force Main project; remaining estimated $4.34 million to be funded in FY 2027/28.
Document type
AgendaPacket
Source document
Granada Community Services District Agenda Packet 2026-08-20

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Granada Community Services District?

Sewer Authority Mid-coastside was awarded this construction contract by Granada Community Services District, as recorded on August 17, 2026. The contract value is $13,228,000 (GMP for construction contract with McGuire Hester); total Option 2 project cost estimated at $16,486,938; GCSD FY 2026/27 share $2,212,515–$2,321,775 depending on table referenced.

How much is the Sewer Authority Mid-coastside contract with Granada Community Services District worth?

The Sewer Authority Mid-coastside contract with Granada Community Services District is valued at $13,228,000 (GMP for construction contract with McGuire Hester); total Option 2 project cost estimated at $16,486,938; GCSD FY 2026/27 share $2,212,515–$2,321,775 depending on table referenced, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Granada Community Services District Agenda Packet 2026-08-20 (AgendaPacket), dated August 17, 2026 from Granada Community Services District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Sewer Authority Mid-coastside hold?

Sewer Authority Mid-coastside may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Sewer Authority Mid-coastside's profile

What is Granada Community Services District currently buying?

Explore Granada Community Services District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Granada Community Services District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free