Emerald High School Construction Change Order Pending Approval
- Disclosed value
- $(5,064,751.00) net change; $652,673.00 additions and $(5,717,424.00) deductions
- From contract
- Document date
- May 28, 2025
The 30-second brief
Dublin Unified School District is considering Change Order No. 06 with BHM for the Emerald High School Phase II construction project. The change order would reduce the contract by a net $5,064,751, bringing the adjusted contract sum to $70,799,145, and extend completion to July 7, 2025.
BHM holds this construction contract with Dublin Unified. Its other public contracts on record include work for Morgantown Monongalia MPO and Town of Shepherdstown.
Term as filed: Contract dated 9/27/2023; 83-day extension from April 15, 2025 to July 7, 2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $(5,064,751.00) net change; $652,673.00 additions and $(5,717,424.00) deductions
- Document date
- May 28, 2025
- Term
- Contract dated 9/27/2023; 83-day extension from April 15, 2025 to July 7, 2025
- Vendor
- BHM
- Agency
- Dublin Unified
- Source document
- Dublin Unified School District Contract Change Order No. 06 Emerald High School Phase II 2025-05-28 (Contract)
BHM's other public contracts
More Dublin Unified contracts
Questions about this contract
Who was awarded the construction contract by Dublin Unified?
BHM was awarded this construction contract by Dublin Unified, as recorded on May 28, 2025. The contract value is $(5,064,751.00) net change; $652,673.00 additions and $(5,717,424.00) deductions.
How much is the BHM contract with Dublin Unified worth?
The BHM contract with Dublin Unified is valued at $(5,064,751.00) net change; $652,673.00 additions and $(5,717,424.00) deductions, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Dublin Unified School District Contract Change Order No. 06 Emerald High School Phase II 2025-05-28 (Contract), dated May 28, 2025 from Dublin Unified. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does BHM hold?
BHM may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Dublin Unified currently buying?
Explore Dublin Unified's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.