CONTRACTRECOMMENDED

Keller Brothers Included In Townhall Bid Recommendations

Dewey Beach Police Department
Disclosed value
$12,343,000 for both phases; $9,253,000 for Phase 1 Townhall and $3,041,500 for Phase 2 EMS; $11,847,000 with acceptance of Alternates 1-9; $11,744,600 with Alternates 1-9 and elimination of phasing
From report
Document date
Jan 25, 2025

The 30-second brief

What it covers

The report ranks Keller Brothers fourth for the base combined-phase and Townhall-only scenarios, but third with Alternates 1-9. Its combined base bid is $12.343 million for 670 construction days, with an $11.847 million amount identified for Alternates 1-9.

Who holds it

Keller Brothers Inc holds this construction contract with Dewey Beach Police Department. Its other public contracts on record include work for Town of Berlin and Montgomery County Public Schools.

What happens next

Term as filed: 670 total construction days; Phase 1: 365 days; Phase 2: 305 days.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$12,343,000 for both phases; $9,253,000 for Phase 1 Townhall and $3,041,500 for Phase 2 EMS; $11,847,000 with acceptance of Alternates 1-9; $11,744,600 with Alternates 1-9 and elimination of phasing
Document date
January 25, 2025
Term
670 total construction days; Phase 1: 365 days; Phase 2: 305 days
Source document
Townhall Project Bid Recommendations 2025-01-25 (Report)

Keller Brothers Inc's other public contracts

More Dewey Beach Police Department contracts

Questions about this contract

Who was awarded the construction contract by Dewey Beach Police Department?

Keller Brothers Inc was awarded this construction contract by Dewey Beach Police Department, as recorded on January 25, 2025. The contract value is $12,343,000 for both phases; $9,253,000 for Phase 1 Townhall and $3,041,500 for Phase 2 EMS; $11,847,000 with acceptance of Alternates 1-9; $11,744,600 with Alternates 1-9 and elimination of phasing.

How much is the Keller Brothers Inc contract with Dewey Beach Police Department worth?

The Keller Brothers Inc contract with Dewey Beach Police Department is valued at $12,343,000 for both phases; $9,253,000 for Phase 1 Townhall and $3,041,500 for Phase 2 EMS; $11,847,000 with acceptance of Alternates 1-9; $11,744,600 with Alternates 1-9 and elimination of phasing, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Townhall Project Bid Recommendations 2025-01-25 (Report), dated January 25, 2025 from Dewey Beach Police Department. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Keller Brothers Inc hold?

Keller Brothers Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Dewey Beach Police Department currently buying?

Explore Dewey Beach Police Department's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →