CONSTRUCTIONAMENDED

PFAS soil removal contract expanded with Elmer’s Crane and Dozer

The Northwest Regional Airport Authority will increase its PFAS Soil Removal Action contract with Elmer’s Crane and Dozer Inc. by $129,960.00 to cover additional excavation, hauling, testing, and gate security. The revised contract totals $258,900.00 with substantial completion still set for April 12, 2026 and final payment by May 25, 2026.

Status
AMENDED
Document date
April 28, 2026
Contract type
CONSTRUCTION
Vendor
Elmer's Crane and Dozer Inc
Agency
Traverse City Airport Commission · MI

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Change Order #1: +$129,960.00; revised contract total $258,900.00
Contract type
CONSTRUCTION
Contract term
Substantial completion April 12, 2026; ready for final payment May 25, 2026; unchanged by this change order
Renewal date
2026-05-25
Renewal
Change Order No. 1 raises the contract price to $258,900.00 while keeping substantial completion at April 12, 2026 and final payment date at May 25, 2026.
Document type
Agenda
Source document
Northwest Regional Airport Authority Regular Meeting Agenda April 28, 2026

Related contracts

Other contracts from Elmer's Crane and Dozer Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Traverse City Airport Commission?

Elmer's Crane and Dozer Inc was awarded this construction contract by Traverse City Airport Commission, as recorded on April 28, 2026. The contract value is Change Order #1: +$129,960.00; revised contract total $258,900.00.

How much is the Elmer's Crane and Dozer Inc contract with Traverse City Airport Commission worth?

The Elmer's Crane and Dozer Inc contract with Traverse City Airport Commission is valued at Change Order #1: +$129,960.00; revised contract total $258,900.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Northwest Regional Airport Authority Regular Meeting Agenda April 28, 2026 (Agenda), dated April 28, 2026 from Traverse City Airport Commission. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Elmer's Crane and Dozer Inc hold?

Elmer's Crane and Dozer Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Elmer's Crane and Dozer Inc's profile

What is Traverse City Airport Commission currently buying?

Explore Traverse City Airport Commission's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Traverse City Airport Commission's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free