Winder Weighs Stormwater Contract Change Order No. 2
- Disclosed value
- $293,560.63 (change order); revised contract total $5,945,981.94; total requested project budget $6,095,981.94
- From agenda
- Document date
- Jul 7, 2026
The 30-second brief
The City of Winder Council is considering Change Order No. 2 with Summit Construction & Development, adding $293,560.63 to the Center Street Stormwater Outfall project and raising the construction contract to $5,945,981.94. With an added $150,000 contingency, the total project budget would be $6,095,981.94, funded primarily by ARPA.
Summit Construction & Development holds this construction contract with City of Winder. Its other public contracts on record include work for City of Woodstock.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $293,560.63 (change order); revised contract total $5,945,981.94; total requested project budget $6,095,981.94
- Document date
- July 7, 2026
- Agency
- City of Winder
- Source document
- City of Winder City Council Agenda 2026-07-07 (Agenda)
Summit Construction & Development's other public contracts
More City of Winder contracts
Questions about this contract
Who was awarded the construction contract by City of Winder?
Summit Construction & Development was awarded this construction contract by City of Winder, as recorded on July 7, 2026. The contract value is $293,560.63 (change order); revised contract total $5,945,981.94; total requested project budget $6,095,981.94.
How much is the Summit Construction & Development contract with City of Winder worth?
The Summit Construction & Development contract with City of Winder is valued at $293,560.63 (change order); revised contract total $5,945,981.94; total requested project budget $6,095,981.94, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in City of Winder City Council Agenda 2026-07-07 (Agenda), dated July 7, 2026 from City of Winder. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Summit Construction & Development hold?
Summit Construction & Development may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Winder currently buying?
Explore City of Winder's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.