Integrity completed major construction on the Cherry Street Lift Station Project, achieving substantial completion in January 2026 and final completion in May 2026. The new lift station is operating with demolition work finished.
INTEGRITY holds this construction contract with City of Wausau. Its other public contracts on record include work for City of Titusville and Bay County.
Term as filed: Mobilized 09/08/2025; Substantial Completion 01/31/2026; Final Completion 05/15/2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- July 14, 2026
- Term
- Mobilized 09/08/2025; Substantial Completion 01/31/2026; Final Completion 05/15/2026
- Vendor
- INTEGRITY
- Agency
- City of Wausau
- Source document
- Wausau Water Works Commission AgendaPacket 2026-07-14 (AgendaPacket)
INTEGRITY's other public contracts
More City of Wausau contracts
Questions about this contract
Who was awarded the construction contract by City of Wausau?
INTEGRITY was awarded this construction contract by City of Wausau, as recorded on July 14, 2026.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Wausau Water Works Commission AgendaPacket 2026-07-14 (AgendaPacket), dated July 14, 2026 from City of Wausau. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does INTEGRITY hold?
INTEGRITY may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of Wausau currently buying?
Explore City of Wausau's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.