Beaudoin Continues Harbor Transformer Slab Work
- Document date
- Nov 29, 2023
The 30-second brief
The Recreational Harbor Authority recorded that Beaudoin poured the concrete transformer slab for the I&M electrical project, indicating ongoing construction work at the harbor. No contract value or term was discussed in the minutes.
BEAUDOIN holds this construction contract with City of St. Joseph. Its other public contracts on record include work for Town of Covert and Southwest Michigan Regional Airport Board.
See every contract and contact at City of St. Joseph.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- November 29, 2023
- Vendor
- BEAUDOIN
- Agency
- City of St. Joseph
- Source document
- City of Saint Joseph Recreational Harbor Authority Minutes 2023-11-29 (Minutes)
BEAUDOIN's other public contracts
More City of St. Joseph contracts
Questions about this contract
Who was awarded the construction contract by City of St. Joseph?
BEAUDOIN was awarded this construction contract by City of St. Joseph, as recorded on November 29, 2023.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in City of Saint Joseph Recreational Harbor Authority Minutes 2023-11-29 (Minutes), dated November 29, 2023 from City of St. Joseph. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does BEAUDOIN hold?
BEAUDOIN may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of St. Joseph currently buying?
Explore City of St. Joseph's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.