CONTRACTRECOMMENDED

SeaTac, Midway Sewer District agree on sewer ILA

City of SeaTac logoCity of SeaTac
Disclosed value
$1,439,781.60 (engineer’s estimate of construction cost; District to reimburse actual direct construction costs plus 10% for construction administration, net of certain side sewer costs borne by the City)
From agendapacket
Document date
Jun 25, 2026

The 30-second brief

What it covers

SeaTac Public Works is proposing an interlocal agreement with Midway Sewer District for the City to construct new gravity sewer collection facilities within the Airport Station Area Pedestrian Improvements Project and be reimbursed for all related costs plus a 10% construction administration fee. The sewer work has an engineer’s estimate of $1,439,781.60 with construction expected to begin in September 2026 and run for about 655 working days.

Who holds it

Midway Sewer District holds this utilities contract with City of SeaTac. Its other public contracts on record include work for Des Moines Pool Metropolitan Park District.

What happens next

Term as filed: Construction estimated to start September 2026 with anticipated duration of 655 working days.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Utilities
Amount
$1,439,781.60 (engineer’s estimate of construction cost; District to reimburse actual direct construction costs plus 10% for construction administration, net of certain side sewer costs borne by the City)
Document date
June 25, 2026
Term
Construction estimated to start September 2026 with anticipated duration of 655 working days
Source document
City of SeaTac Transportation and Public Works Committee Agenda Packet 2026-06-25 (AgendaPacket)

Midway Sewer District's other public contracts

More City of SeaTac contracts

Questions about this contract

Who was awarded the utilities contract by City of SeaTac?

Midway Sewer District was awarded this utilities contract by City of SeaTac, as recorded on June 25, 2026. The contract value is $1,439,781.60 (engineer’s estimate of construction cost; District to reimburse actual direct construction costs plus 10% for construction administration, net of certain side sewer costs borne by the City).

How much is the Midway Sewer District contract with City of SeaTac worth?

The Midway Sewer District contract with City of SeaTac is valued at $1,439,781.60 (engineer’s estimate of construction cost; District to reimburse actual direct construction costs plus 10% for construction administration, net of certain side sewer costs borne by the City), covering utilities work.

What type of contract is this?

This is a Utilities contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of SeaTac Transportation and Public Works Committee Agenda Packet 2026-06-25 (AgendaPacket), dated June 25, 2026 from City of SeaTac. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Midway Sewer District hold?

Midway Sewer District may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of SeaTac currently buying?

Explore City of SeaTac's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →