Liquidated Damages Revoked for KW Underground
- Document date
- Aug 2, 2022
The 30-second brief
The Ocilla City Council unanimously voted to revoke the liquidation damage assessment previously imposed on KW Underground for the McKinley Street Project. The change follows contractor requests for additional time due to supply constraints on materials like concrete pipes.
Kw Underground holds this construction contract with City of Ocilla. Its other public contracts on record include work for Bibb County.
See every contract and contact at City of Ocilla.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- August 2, 2022
- Vendor
- Kw Underground
- Agency
- City of Ocilla
- Source document
- city-of-ocilla-council-meeting-minutes-august-2-2022_1a3.pdf (Minutes)
Kw Underground's other public contracts
More City of Ocilla contracts
Questions about this contract
Who was awarded the construction contract by City of Ocilla?
Kw Underground was awarded this construction contract by City of Ocilla, as recorded on August 2, 2022.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in city-of-ocilla-council-meeting-minutes-august-2-2022_1a3.pdf (Minutes), dated August 2, 2022 from City of Ocilla. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Kw Underground hold?
Kw Underground may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of Ocilla currently buying?
Explore City of Ocilla's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.