Change Order Recommended for Well #9 Generator
- Disclosed value
- $15,213 (change order); new total project cost approximately $284,000
- From minutes
- Document date
- Dec 23, 2025
The 30-second brief
The Infrastructure Committee recommended a $15,213 change order with PowerLink to add a new disconnect switch to the Well #9 generator project, bringing the total project cost to about $284,000 while remaining under budget. The expense will be covered by remaining ARPA funds allocated for the project.
POWERLINK holds this equipment contract with City of Harvard city. Its other public contracts on record include work for Town of Cumberland and Lake Zurich CUSD 95.
See every contract and contact at City of Harvard city.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Equipment
- Amount
- $15,213 (change order); new total project cost approximately $284,000
- Document date
- December 23, 2025
- Vendor
- POWERLINK
- Agency
- City of Harvard city
- Source document
- Infrastructure Committee Meeting Minutes December 2025 (Minutes)
POWERLINK's other public contracts
More City of Harvard city contracts
Questions about this contract
Who was awarded the equipment contract by City of Harvard city?
POWERLINK was awarded this equipment contract by City of Harvard city, as recorded on December 23, 2025. The contract value is $15,213 (change order); new total project cost approximately $284,000.
How much is the POWERLINK contract with City of Harvard city worth?
The POWERLINK contract with City of Harvard city is valued at $15,213 (change order); new total project cost approximately $284,000, covering equipment work.
What type of contract is this?
This is a Equipment contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Infrastructure Committee Meeting Minutes December 2025 (Minutes), dated December 23, 2025 from City of Harvard city. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does POWERLINK hold?
POWERLINK may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Harvard city currently buying?
Explore City of Harvard city's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.