Main Avenue Paving Change Order Approved for Koski
- Disclosed value
- Not to exceed $165,000; Koski's bid was $139,658, with approximately $25,000 reserved as a striping contingency
- From agendapacket
- Document date
- Oct 19, 2026
- Term
- Completion required by October 31, 2026
- Renews
- Free account
The 30-second brief
Ashtabula City Council approved a change order with KOSKI CONSTRUCION CO. of up to $165,000 for Main Avenue resurfacing and striping. The Appalachian Community Grant Program will fully fund the added work, which must be completed by October 31, 2026.
Koski Construcion Company holds this construction contract with City of Ashtabula. Its other public contracts on record include work for Town of Ashtabula.
The renewal date is on record. A free account shows it, with the renewals for every City of Ashtabula contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Not to exceed $165,000; Koski's bid was $139,658, with approximately $25,000 reserved as a striping contingency
- Document date
- October 19, 2026
- Term
- Completion required by October 31, 2026
- Renews
- Free account
- Agency
- City of Ashtabula
- Source document
- City of Ashtabula AgendaPacket Regular Meeting October 19, 2026 (AgendaPacket)
Koski Construcion Company's other public contracts
More City of Ashtabula contracts
Questions about this contract
Who was awarded the construction contract by City of Ashtabula?
Koski Construcion Company was awarded this construction contract by City of Ashtabula, as recorded on October 19, 2026. The contract value is Not to exceed $165,000; Koski's bid was $139,658, with approximately $25,000 reserved as a striping contingency.
How much is the Koski Construcion Company contract with City of Ashtabula worth?
The Koski Construcion Company contract with City of Ashtabula is valued at Not to exceed $165,000; Koski's bid was $139,658, with approximately $25,000 reserved as a striping contingency, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in City of Ashtabula AgendaPacket Regular Meeting October 19, 2026 (AgendaPacket), dated October 19, 2026 from City of Ashtabula. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Koski Construcion Company hold?
Koski Construcion Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Ashtabula currently buying?
Explore City of Ashtabula's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.