CONTRACTAPPROVED

Cheney School District Awards Construction Contract to Leone & Keeble Inc (February 2026)

Cheney School District logoCheney School District
Disclosed value
$2,107,000 (not including sales tax to be paid based on the Contract Sum)
From agreement
Approved
Feb 5, 2026
Renews
Free account

The 30-second brief

What it covers

Cheney School District No. 360 approved a $2,107,000 construction contract with Leone & Keeble, Inc. to expand kitchens at Salnave and Windsor Elementary Schools and upgrade switchgear at Windsor Elementary School. Work will occur from March through December 2026, with liquidated damages for delays and standard public works insurance, bonding, and prevailing wage requirements in place.

Who holds it

Leone & Keeble Inc holds this construction contract with Cheney School District. Its other public contracts on record include work for Central Valley Public School District 3 and Union Gap School District.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every Cheney School District contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$2,107,000 (not including sales tax to be paid based on the Contract Sum)
Document date
February 5, 2026
Term
Anticipated start March 2, 2026, with portions completing between August 15, 2026 and December 18, 2026; Final Completion for each portion within 30 days after its Substantial Completion
Renews
Free account
Vendor
Leone & Keeble Inc
Source document
Cheney School District Agreement Kitchen Expansions and Switchgear Upgrades 2026-02-05 (Agreement)

Leone & Keeble Inc's other public contracts

More Cheney School District contracts

Questions about this contract

Who was awarded the construction contract by Cheney School District?

Leone & Keeble Inc was awarded this construction contract by Cheney School District, as recorded on February 5, 2026. The contract value is $2,107,000 (not including sales tax to be paid based on the Contract Sum).

How much is the Leone & Keeble Inc contract with Cheney School District worth?

The Leone & Keeble Inc contract with Cheney School District is valued at $2,107,000 (not including sales tax to be paid based on the Contract Sum), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agreement record.

Where was this contract approved?

This contract appears in Cheney School District Agreement Kitchen Expansions and Switchgear Upgrades 2026-02-05 (Agreement), dated February 5, 2026 from Cheney School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is Cheney School District currently buying?

Explore Cheney School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →