West Parking Lot Change Order Recommended for Midwest Asphalt
- Disclosed value
- $36,754.00
- From contract
- Document date
- Jul 27, 2026
The 30-second brief
Champaign Community Unit School District 4 is recommending a $36,754.00 change order with Midwest Asphalt Company for west-lot subgrade improvements at Franklin STEAM Academy. The work covers organic-soil removal, compact aggregate placement, overdig testing, and asphalt-equipment remobilization, while maintaining substantial completion on September 25, 2026.
Midwest Asphalt Company holds this construction contract with Champaign CUSD 4. Its other public contracts on record include work for Danville Police Department and Town of Danville.
Term as filed: Contract time unchanged; new date of Substantial Completion September 25, 2026.
See who signed off on this $36.8K contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $36,754.00
- Document date
- July 27, 2026
- Term
- Contract time unchanged; new date of Substantial Completion September 25, 2026
- Vendor
- Midwest Asphalt Company
- Agency
- Champaign CUSD 4
- Source document
- Champaign Community Unit School District 4 Contract Change Orders #03 & #04 Franklin Steam Academy Parking Lot Expansion 2026-07-27 (Contract)
Midwest Asphalt Company's other public contracts
More Champaign CUSD 4 contracts
Questions about this contract
Who was awarded the construction contract by Champaign CUSD 4?
Midwest Asphalt Company was awarded this construction contract by Champaign CUSD 4, as recorded on July 27, 2026. The contract value is $36,754.00.
How much is the Midwest Asphalt Company contract with Champaign CUSD 4 worth?
The Midwest Asphalt Company contract with Champaign CUSD 4 is valued at $36,754.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Champaign Community Unit School District 4 Contract Change Orders #03 & #04 Franklin Steam Academy Parking Lot Expansion 2026-07-27 (Contract), dated July 27, 2026 from Champaign CUSD 4. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Midwest Asphalt Company hold?
Midwest Asphalt Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Champaign CUSD 4 currently buying?
Explore Champaign CUSD 4's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.