CONTRACTAMENDED

Sam Hill & Sons CAPP Pipeline Contract Increased

Carpinteria Valley Water District logoCarpinteria Valley Water District
Disclosed value
Additional change-order authorization not to exceed $150,000; contingency increased from $360,135 to $510,135; total contract authorization increased from $3,960,000 to $4,110,000
From agendapacket
Document date
Oct 24, 2026
Term
Ongoing as of October 14, 2026

The 30-second brief

What it covers

Carpinteria Valley Water District authorized up to $150,000 in additional change orders for Sam Hill & Sons’ CAPP Conveyance Pipelines contract. The action raised total contract authorization to $4.11 million.

Who holds it

Sam Hill & Sons Inc holds this construction contract with Carpinteria Valley Water District. Its other public contracts on record include work for Carpinteria Sanitary District and Channel Island Beach Community Services Dist.

What happens next

Term as filed: Ongoing as of October 14, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Additional change-order authorization not to exceed $150,000; contingency increased from $360,135 to $510,135; total contract authorization increased from $3,960,000 to $4,110,000
Document date
October 24, 2026
Term
Ongoing as of October 14, 2026
Source document
Carpinteria Valley Water District AgendaPacket Board Meeting 2026-10-28 (AgendaPacket)

Sam Hill & Sons Inc's other public contracts

More Carpinteria Valley Water District contracts

Questions about this contract

Who was awarded the construction contract by Carpinteria Valley Water District?

Sam Hill & Sons Inc was awarded this construction contract by Carpinteria Valley Water District, as recorded on October 24, 2026. The contract value is Additional change-order authorization not to exceed $150,000; contingency increased from $360,135 to $510,135; total contract authorization increased from $3,960,000 to $4,110,000.

How much is the Sam Hill & Sons Inc contract with Carpinteria Valley Water District worth?

The Sam Hill & Sons Inc contract with Carpinteria Valley Water District is valued at Additional change-order authorization not to exceed $150,000; contingency increased from $360,135 to $510,135; total contract authorization increased from $3,960,000 to $4,110,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Carpinteria Valley Water District AgendaPacket Board Meeting 2026-10-28 (AgendaPacket), dated October 24, 2026 from Carpinteria Valley Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Sam Hill & Sons Inc hold?

Sam Hill & Sons Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Carpinteria Valley Water District currently buying?

Explore Carpinteria Valley Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →