District Issues Second Fire Alarm Change Order
- Disclosed value
- $28,210.15 (change order); new total contract amount $1,757,540.56
- From contract
- Document date
- Mar 17, 2026
The 30-second brief
Campbell Union High School District issued Change Order No. 2 with Aram Electric for the Westmont Fire Alarm Replacement project, adding additional detectors and relay modules for $28,210.15 and extending the schedule by 10 days. The amendment brings the total contract value to $1,757,540.56 with a revised completion date of March 6, 2026.
Aram Electric holds this construction contract with Campbell Union High.
Term as filed: Contract completion date extended from 02/27/2026 to 03/06/2026; original contract date 06/12/2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $28,210.15 (change order); new total contract amount $1,757,540.56
- Document date
- March 17, 2026
- Term
- Contract completion date extended from 02/27/2026 to 03/06/2026; original contract date 06/12/2025
- Vendor
- Aram Electric
- Agency
- Campbell Union High
- Source document
- Campbell Union High School District Contract Change Order 2 2026-03-17 (Contract)
Aram Electric's other public contracts
More Campbell Union High contracts
Questions about this contract
Who was awarded the construction contract by Campbell Union High?
Aram Electric was awarded this construction contract by Campbell Union High, as recorded on March 17, 2026. The contract value is $28,210.15 (change order); new total contract amount $1,757,540.56.
How much is the Aram Electric contract with Campbell Union High worth?
The Aram Electric contract with Campbell Union High is valued at $28,210.15 (change order); new total contract amount $1,757,540.56, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Campbell Union High School District Contract Change Order 2 2026-03-17 (Contract), dated March 17, 2026 from Campbell Union High. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Aram Electric hold?
Aram Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Campbell Union High currently buying?
Explore Campbell Union High's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.