Water system change order increases contract value
Bladen CountyCounty · NC- Disclosed value
- Increase of this Change Order: $156,239.00 (new total Contract Price $1,074,424.00; original Contract Price $918,185.00)
- From contract
- Document date
- May 19, 2025
The 30-second brief
The Bladen County Water District executed Change Order No. 1 with Herring-Rivenbark, Inc. for the Water System Upgrades and Extensions - Chemours project, increasing the contract by $156,239.00 to a new total of $1,074,424.00 while leaving the 180-day substantial completion and 210-day final payment timelines unchanged. The scope adjustment adds water main extension along Purdie Hall Road and reduces pipe installation along Pone Loop Road, supported by detailed quantity tabulations.
Herring-rivenbark Inc holds this construction contract with Bladen County. Its other public contracts on record include work for Town of Spring Hope and Bladen Housing Authority.
Term as filed: Contract Times unchanged: 180 days to substantial completion; 210 days to ready for final payment.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of this Change Order: $156,239.00 (new total Contract Price $1,074,424.00; original Contract Price $918,185.00)
- Document date
- May 19, 2025
- Term
- Contract Times unchanged: 180 days to substantial completion; 210 days to ready for final payment
- Vendor
- Herring-rivenbark Inc
- Agency
- Bladen County
- Source document
- Bladen County Water District Change Order No. 1 2025-05-19 (Contract)
Herring-rivenbark Inc's other public contracts
More Bladen County contracts
Questions about this contract
Who was awarded the construction contract by Bladen County?
Herring-rivenbark Inc was awarded this construction contract by Bladen County, as recorded on May 19, 2025. The contract value is Increase of this Change Order: $156,239.00 (new total Contract Price $1,074,424.00; original Contract Price $918,185.00).
How much is the Herring-rivenbark Inc contract with Bladen County worth?
The Herring-rivenbark Inc contract with Bladen County is valued at Increase of this Change Order: $156,239.00 (new total Contract Price $1,074,424.00; original Contract Price $918,185.00), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Bladen County Water District Change Order No. 1 2025-05-19 (Contract), dated May 19, 2025 from Bladen County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Herring-rivenbark Inc hold?
Herring-rivenbark Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Bladen County currently buying?
Explore Bladen County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.