Original Contract Amount $355,076.22; Net Total of Change Orders to Contract $7,004.00; Original Purchase Order Total $475,833.78; Net Total of Change Orders to Purchase Orders $0.00; Total Cost of Construction $837,914.00
From report
Approved
Aug 12, 2026

The 30-second brief

What it covers

Bellevue Independent Board of Education sought approval of the BG-4 for The Motz Group’s work on the Bellevue High School Gilligan Stadium and Ben Flora improvements. The form lists an original contract amount of $355,076.22, change orders of $7,004.00, and total construction cost of $837,914.00.

Who holds it

The Motz Group holds this construction contract with Bellevue Independent School District. Its other public contracts on record include work for Greenville County School District and Dr Robert Ketterer CS Inc.

What happens next

Term as filed: Project initiation through substantial completion; BG4 Date 7/17/2026; BG4 Board Order Date 8/19/2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Original Contract Amount $355,076.22; Net Total of Change Orders to Contract $7,004.00; Original Purchase Order Total $475,833.78; Net Total of Change Orders to Purchase Orders $0.00; Total Cost of Construction $837,914.00
Document date
August 12, 2026
Term
Project initiation through substantial completion; BG4 Date 7/17/2026; BG4 Board Order Date 8/19/2026
Source document
Bellevue Independent Board of Education Report BG-4 Form 2026-08-12 (Report)

The Motz Group's other public contracts

More Bellevue Independent School District contracts

Questions about this contract

Who was awarded the construction contract by Bellevue Independent School District?

The Motz Group was awarded this construction contract by Bellevue Independent School District, as recorded on August 12, 2026. The contract value is Original Contract Amount $355,076.22; Net Total of Change Orders to Contract $7,004.00; Original Purchase Order Total $475,833.78; Net Total of Change Orders to Purchase Orders $0.00; Total Cost of Construction $837,914.00.

How much is the The Motz Group contract with Bellevue Independent School District worth?

The The Motz Group contract with Bellevue Independent School District is valued at Original Contract Amount $355,076.22; Net Total of Change Orders to Contract $7,004.00; Original Purchase Order Total $475,833.78; Net Total of Change Orders to Purchase Orders $0.00; Total Cost of Construction $837,914.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Bellevue Independent Board of Education Report BG-4 Form 2026-08-12 (Report), dated August 12, 2026 from Bellevue Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does The Motz Group hold?

The Motz Group may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Bellevue Independent School District currently buying?

Explore Bellevue Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →