Downtown Utilities Contract Amended for Jimmy R. Lynch & Sons Inc.
- Disclosed value
- Sewer contract increased by $206,540.92 to $4,810,461.32; Water contract increased by $36,526.72 to $9,396,648.56
- From agenda
- Document date
- Mar 3, 2026
- Term
- 15 additional days added
The 30-second brief
The Burlington City Council approved Change Order No. 2 to the Downtown Utilities Water and Sewer contracts with Jimmy R. Lynch and Sons, Inc., increasing the contract totals to $4,810,461.32 (sewer) and $9,396,648.56 (water), with 15 additional contract days. The change order addresses updated work scopes and remains within the approved project contingency.
Jimmy R Lynch & Sons Inc holds this construction contract with City of Burlington. Its other public contracts on record include work for Town of Pilot Mountain and City of Eden.
Term as filed: 15 additional days added.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Sewer contract increased by $206,540.92 to $4,810,461.32; Water contract increased by $36,526.72 to $9,396,648.56
- Document date
- March 3, 2026
- Term
- 15 additional days added
- Vendor
- Jimmy R Lynch & Sons Inc
- Agency
- City of Burlington
- Source document
- City of Burlington City Council Meeting Agenda March 2026 (Agenda)
Jimmy R Lynch & Sons Inc's other public contracts
More City of Burlington contracts
Questions about this contract
Who was awarded the construction contract by City of Burlington?
Jimmy R Lynch & Sons Inc was awarded this construction contract by City of Burlington, as recorded on March 3, 2026. The contract value is Sewer contract increased by $206,540.92 to $4,810,461.32; Water contract increased by $36,526.72 to $9,396,648.56.
How much is the Jimmy R Lynch & Sons Inc contract with City of Burlington worth?
The Jimmy R Lynch & Sons Inc contract with City of Burlington is valued at Sewer contract increased by $206,540.92 to $4,810,461.32; Water contract increased by $36,526.72 to $9,396,648.56, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in City of Burlington City Council Meeting Agenda March 2026 (Agenda), dated March 3, 2026 from City of Burlington. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is City of Burlington currently buying?
Explore City of Burlington's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.