Barrington CUSD 220 Awards Construction Contract to Pepper Construction Company (May 2026)
- Disclosed value
- Final Cost Estimate: $55,188,523; Total Project Work Order #12: $55,188,523.68; Current Project Total: $66,648,782.80
- From contract
- Approved
- May 28, 2026
- Term
- June 1, 2026 – August 4, 2028
- Renews
- Free account
The 30-second brief
Barrington Community Unit School District 220 approved Project Work Order #12 R2 with Pepper Construction Company for additions and renovations at Barrington High School and Barrington Middle School. The work order totals $55.19 million, begins June 1, 2026, and requires substantial completion by August 4, 2028.
Pepper Construction Company holds this construction contract with Barrington CUSD 220. Its other public contracts on record include work for Township HSD 214 and Hinsdale Twp HSD 86.
The renewal date is on record. A free account shows it, with the renewals for every Barrington CUSD 220 contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Final Cost Estimate: $55,188,523; Total Project Work Order #12: $55,188,523.68; Current Project Total: $66,648,782.80
- Document date
- May 28, 2026
- Term
- June 1, 2026 – August 4, 2028
- Renews
- Free account
- Agency
- Barrington CUSD 220
- Source document
- Barrington Community Unit School District 220 Contract Project Work Order #12 R2 Barrington High School Fine Arts Addition & Remodeling and Barrington Middle School Science Classroom Renovations 2026-05-28 (Contract)
Pepper Construction Company's other public contracts
More Barrington CUSD 220 contracts
Questions about this contract
Who was awarded the construction contract by Barrington CUSD 220?
Pepper Construction Company was awarded this construction contract by Barrington CUSD 220, as recorded on May 28, 2026. The contract value is Final Cost Estimate: $55,188,523; Total Project Work Order #12: $55,188,523.68; Current Project Total: $66,648,782.80.
How much is the Pepper Construction Company contract with Barrington CUSD 220 worth?
The Pepper Construction Company contract with Barrington CUSD 220 is valued at Final Cost Estimate: $55,188,523; Total Project Work Order #12: $55,188,523.68; Current Project Total: $66,648,782.80, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Barrington Community Unit School District 220 Contract Project Work Order #12 R2 Barrington High School Fine Arts Addition & Remodeling and Barrington Middle School Science Classroom Renovations 2026-05-28 (Contract), dated May 28, 2026 from Barrington CUSD 220. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Pepper Construction Company hold?
Pepper Construction Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Barrington CUSD 220 currently buying?
Explore Barrington CUSD 220's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.