Hensel Phelps ATCT Contract Amended For Delay Costs
- Disclosed value
- $2,387,032 incremental change order; total contract $386,375,618
- From agendapacket
- Document date
- Oct 9, 2026
- Term
- 184 additional calendar days
The 30-second brief
The Authority approved Change Order No. 10 with Hensel Phelps for $2.387 million to cover extended general conditions from Air Traffic Control Tower project delays. The change adds 184 calendar days and brings the total contract to $386.376 million.
Hensel Phelps holds this construction contract with Asheville Regional Airport Authority. Its other public contracts on record include work for Austin - Airport Advisory Commission and Town of Windsor.
Term as filed: 184 additional calendar days.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $2,387,032 incremental change order; total contract $386,375,618
- Document date
- October 9, 2026
- Term
- 184 additional calendar days
- Vendor
- Hensel Phelps
- Source document
- Greater Asheville Regional Airport Authority Agenda Packet 2026-10-09 (AgendaPacket)
Hensel Phelps's other public contracts
More Asheville Regional Airport Authority contracts
Questions about this contract
Who was awarded the construction contract by Asheville Regional Airport Authority?
Hensel Phelps was awarded this construction contract by Asheville Regional Airport Authority, as recorded on October 9, 2026. The contract value is $2,387,032 incremental change order; total contract $386,375,618.
How much is the Hensel Phelps contract with Asheville Regional Airport Authority worth?
The Hensel Phelps contract with Asheville Regional Airport Authority is valued at $2,387,032 incremental change order; total contract $386,375,618, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Greater Asheville Regional Airport Authority Agenda Packet 2026-10-09 (AgendaPacket), dated October 9, 2026 from Asheville Regional Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Hensel Phelps hold?
Hensel Phelps may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Asheville Regional Airport Authority currently buying?
Explore Asheville Regional Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.