SR 69 Lee Blvd Segment Work by Asphalt Paving

Dept. of Transportation | State of Arizona logoDept. of Transportation | State of Arizona
Document date
Jun 1, 2026

The 30-second brief

What it covers

Asphalt Paving & Supply, Inc. is reconstructing SR 69 from Lee Blvd to east of Walker Road, with the project 67% complete and 79% of time elapsed. The work focuses on improving pavement and roadway conditions.

Who holds it

Asphalt Paving & Supply Inc holds this construction contract with Dept. of Transportation | State of Arizona. Its other public contracts on record include work for Yavapai County and Arizona Department of Transportation.

See every contract and contact at Dept. of Transportation | State of Arizona.

See every contract

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
June 1, 2026
Vendor
Asphalt Paving & Supply Inc
Source document
Arizona Department of Transportation State Engineer's Report June 2026 (Report)

Asphalt Paving & Supply Inc's other public contracts

More Dept. of Transportation | State of Arizona contracts

Questions about this contract

Who was awarded the construction contract by Dept. of Transportation | State of Arizona?

Asphalt Paving & Supply Inc was awarded this construction contract by Dept. of Transportation | State of Arizona, as recorded on June 1, 2026.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Arizona Department of Transportation State Engineer's Report June 2026 (Report), dated June 1, 2026 from Dept. of Transportation | State of Arizona. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What is Dept. of Transportation | State of Arizona currently buying?

Explore Dept. of Transportation | State of Arizona's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →